On a small project, scheduling each team member's hours by hand works well. Once a project has dozens of tasks, and their dates and assignees keep changing, keeping allocations in step with the plan becomes a job of its own. Every task date change means another edit on someone's schedule, and the two drift apart as soon as someone forgets.
Each project in Rocketlane uses one of two allocation modes to handle this:
- Auto allocate: the project generates allocations from the effort, dates, and assignees on its tasks or phases, and keeps them in sync as the plan changes.
- Manual: project managers and resource managers create and edit allocations directly on the Resource Management timeline, independently of task effort.
This article explains how each mode behaves, how to choose between them, how to switch, and how to move a project's dates without leaving its allocations behind.
In this article
- Before You Start
- How the Two Allocation Modes Compare
- Choosing an Allocation Mode
- How Auto-Allocate Calculates Hours
- Turn On Auto-Allocate
- Working in an Auto-Allocated Project
- Working in a Manually Allocated Project
- Shift Project Dates Together With Allocations
- Turn Off Auto-Allocate
- Projects Created From Templates
- FAQ
- Summary
Before You Start
- Plan: Auto-allocate is part of Resource Management, available on the Premium and Enterprise plans.
- Permissions:
- Turning auto-allocate on or off needs the Can turn auto-allocations on/off for a project permission.
- The More actions menu on the Resource Management Projects tab only appears for users who can edit project allocations.
- Task details auto-allocate needs: a task produces allocations only when it has:
- a start date or a due date (if only one is set, the other is treated as the same date)
- an effort greater than zero
- at least one assignee who is a team member, partner user, or one of your own teams
Tasks without these produce no allocations. On a phase-level project, a phase needs dates and at least one team member with effort greater than zero.
- Important: Turning auto-allocate on deletes every existing allocation on the project, including allocations created by hand and any values in allocation custom fields. This cannot be undone. Export the project's allocations first if they need to be kept.
How the Two Allocation Modes Compare
| Area | Auto allocate | Manual |
|---|---|---|
| Where allocations come from | Generated from task or phase effort, dates, and assignees | Created on the Resource Management timeline, or copied from the template the project was created from |
| Effect of changing task effort, dates, or assignees | Allocations update to match | No effect on allocations |
| Editing allocations on the timeline | Not available. All allocation fields are read-only. | Available: dates, hours, weekends, billable, soft or hard, custom fields |
| Splitting an allocation | Not available | Available |
| Creating or deleting allocations directly | Not available | Available |
| Soft allocations | Not available. Generated allocations are always hard. | Available (Enterprise) |
| Moving allocations when project dates shift | Automatic, because task dates drive allocations | Only when Shift all allocation is selected while shifting the project dates |
| 24-hour-per-day limit within a project | Not enforced | Enforced |
| Staffing with Resource AI | Not available. People are staffed through task assignments. | Available |
Choosing an Allocation Mode
Auto allocate can be useful when:
- The team reliably fills in effort, dates, and assignees on tasks or phases, and the schedule should follow the plan without separate upkeep.
- The project plan changes often, and re-editing allocations after every change would take too long.
- The schedule can be a direct result of the plan, with no hand-tuning per person.
Manual allocation can be useful when:
- Someone's schedule needs to differ from what their task effort implies. For example, spreading 20 hours of review work across a month at a deliberately slow pace.
- Allocations need soft or hard status, custom field values, splits, or per-allocation edits.
- Tasks don't carry effort, dates, and assignees, so auto-allocate would have nothing to work from.
- Staffing is planned at the project level (for example, "one consultant at 50% for three months") rather than task by task.
How Auto-Allocate Calculates Hours
The result is predictable once the formula is clear.
With Task-Level Effort Planning
For each task and each assignee:
Hours per day = (task effort ÷ number of assignees) ÷ number of counted days in the task's date range
The result is one allocation spanning the task's start and due dates, at a flat rate per day. Hours are spread evenly, never front-loaded or tapered.
- Effort is divided between assignees, not duplicated. A 30-hour task with three assignees produces 10 hours for each person, not 30 each.
- With a custom effort split, each assignee's own effort figure is used instead of an equal share. Anyone whose effort is zero gets no allocation.
- Weekends aren't counted unless Include weekend is selected for that assignee in the task's Effort section. Because this is set per assignee, two people on the same task can get different rates per day.
With Phase-Level Effort Planning
At phase level, each team member already has their own effort figure for the phase, so nothing is divided:
Hours per day = that person's phase effort ÷ number of counted days in the phase's date range
Team members with no effort, or zero effort, are skipped.
Worked Example
Three tasks are assigned to the same person, with weekends included:
| Task | Effort | Date range |
|---|---|---|
| Task A | 10 hours | 6 days |
| Task B | 10 hours | 6 days |
| Task C | 10 hours | 7 days |
Auto-allocate creates three separate allocations at 1h 40m per day, 1h 40m per day, and 1h 25m per day. One allocation is created per task, per assignee, per budget, so these appear as three allocations on the same person rather than one merged allocation.
Behaviors to Know
- Holidays are not excluded. Weekends can be skipped, but a public holiday inside a task's date range still receives hours. Time off is shown on the Resource Management timeline, but it does not block allocations in either mode. For more information, refer to How do Time Offs reflect in resource management.
- There is a minimum of one minute per day. A very small effort spread over a long date range can produce more allocated time than the effort entered. A 10-minute task spread across 60 days becomes 60 minutes of allocation.
- The 24-hour daily limit doesn't apply. Manual allocations cannot exceed 24 hours per person per day within one project. Auto-allocate does not apply this check, so three 10-hour tasks on the same person and the same day generate 30 hours, with no warning. The person's row shows the over 100% colour on the grid. To fix it, change the task plan.
- Accounts that allocate in hours per week have generated allocations aligned to Monday-to-Sunday weeks, with partial weeks prorated. Total allocated hours stay the same.
Turn On Auto-Allocate
Auto-allocate can be turned on from two places. Only the Resource Management route asks for confirmation.
From the Resource Management Projects Tab
- Go to Resource Management > Projects.

- Open More actions on the project's row.
- Select Enable auto-allocate.

- Review the Enable auto-allocate? confirmation. It reads: "If you enable auto-allocate, time allocations for team members will be automatically created based on effort, dates and assignees. Auto-allocate will overwrite any existing time allocations on the project."
- Confirm.

The project shows an auto-allocate icon next to its name. Hovering over it shows Auto-allocate is on.

From Project Settings
- Open the project and go to Settings > Resource management.
- Under Set allocation mode, select Auto allocate.
Working in an Auto-Allocated Project
What Is Read-Only
- Allocations cannot be created or deleted on the timeline. Delete all is unavailable and shows Auto-allocate is ON.
- Opening an allocation shows Auto-allocated for: with a link to the task or phase behind it. Dates, hours, weekends, billable status, soft or hard status, and custom fields are all read-only.
- Split time and splitting from the allocation drawer are not available.
- Turn all allocations soft and Turn all allocations hard are not available, because generated allocations are always hard.
- Resource AI doesn't staff auto-allocated projects. Its Plan your team step shows "This is an auto allocated project." Assign people to tasks instead.
To change an allocation, change its source: the task or phase effort, dates, or assignees.

Find the Task or Phase Behind an Allocation
- Select an allocation on the timeline, or the link next to Auto-allocated for: inside an open allocation.
- Review the list. It is titled Tasks contributing to allocations on task-level projects, or Phases contributing to allocations on phase-level projects. Each row shows the task or phase name, its effort, its assignee (for tasks), and its due date.
- Select a row to open that task or phase, and make the change there.

Changes That Update Allocations
On a task, allocations update when any of these change:
- Start date or due date
- Effort
- Assignees (added, removed, or replaced)
- Split effort among assignees (Equal or Custom)
- Include weekend for an assignee
- The task's default billable setting
On a phase, allocations update when its start date, due date, team members, any team member's effort, or weekend inclusion change.
Setting a task's or phase's effort to zero removes the allocations it created.
These changes do not update allocations: task status, name, description, priority, and custom fields.
These events regenerate all of the project's allocations at once:
- Turning on auto-allocate
- Changing the effort planning level
- Deleting a task
- Importing a template into the project
How Quickly Updates Appear
Allocations usually update as part of the same change, and the timeline refreshes without reloading. When several people edit the same project at the same time, updates are queued and can take a few minutes to appear. Reports such as the portfolio report and Time analytics refresh on their own schedule, so a short delay after a change is expected.
Working in a Manually Allocated Project
On a manually allocated project, allocations are independent of the project plan.
- Task and phase effort do not create allocations. Effort entered on tasks is still used for estimates and reports, but it does not schedule anyone. Allocations must be added on the Resource Management timeline.
- Changing task dates, effort, or assignees does not change allocations. If a task moves by two weeks, the allocations covering that work stay where they are until someone moves them.
- Allocations can be fully edited: dates, hours per day, weekends, billable status, soft or hard status, custom fields, and splits.
To add, edit, split, or delete allocations, refer to Managing Allocations on the Resource Management Timeline.
Shift Project Dates Together With Allocations
When a project's start is delayed or brought forward, the plan and the allocations both need to move. How this works depends on the allocation mode.
| Allocation mode | What to do |
|---|---|
| Auto allocate | Shift the project plan in any way. Allocations follow the new task and phase dates automatically. |
| Manual | Use Shift project dates in Resource Management and select Shift all allocation. Shifting dates from the project plan's Timeline view moves phases and tasks only, not allocations. |
Shift a Manually Allocated Project and Its Allocations
- Go to Resource Management > Projects.
- Open More actions on the project's row and select Shift project dates.
- Under Shift to, select the new start date. Shifting the project start date shifts the dates of all phases and tasks in the project.
- Select Shift all allocation. The option shows how many days the allocations will move by. It is cleared by default.
- Confirm.
Each allocation moves by the same number of days as the project start date, and keeps its length in working days.
To move only some allocations, for example for one team member or from a specific date onwards, raise a shift allocation request. For more information, refer to How to manage Resource requests in Rocketlane. Shift allocation requests and shift allocation automations are not available on auto-allocated projects, where allocations always follow the plan.
Turn Off Auto-Allocate
- Go to Resource Management > Projects.
- Open More actions on the project's row and select Disable auto-allocate.
- Review the Disable auto-allocate? confirmation. It reads: "If you disable auto-allocate, the system will stop automatically updating time allocations based on changes to effort, dates and assignments."
- Confirm.
Alternatively, open the project and go to Settings > Resource management and select Manual under Set allocation mode. This applies immediately, without confirmation.
Turning off auto-allocate does not delete anything:
- Existing allocations keep the same hours, dates, and daily breakdown. Allocated hours, financial forecasts, and report totals stay the same immediately after the switch.
- The allocations become editable, so they can be moved, resized, split, or deleted like any manual allocation.
- Previously generated allocations can still show Auto-allocated for: and their source task. This records where the allocation came from. It does not mean the allocation is still being updated.
- From this point, changes to task effort, dates, or assignees no longer update allocations.
Projects Created From Templates
Templates have their own allocation mode. For more information, refer to How to Enable and Configure Auto-allocate in a Template.
- A project created from a template uses the template's allocation mode.
- If the project is manually allocated, the template's allocations are copied into the project.
- If the project uses auto-allocate, the template's allocations are not copied. Allocations are generated from the project's tasks or phases instead.
- Importing a template into an existing auto-allocated project regenerates all of the project's allocations.
FAQ
Why Doesn't Task Effort Create Any Allocations on My Project?
The project uses manual allocation. On manually allocated projects, effort is an estimate only, and allocations must be added on the Resource Management timeline. To generate allocations from effort, turn on auto-allocate, keeping in mind that this deletes the project's existing allocations.
I Shifted the Project Plan. Why Didn't the Allocations Move?
On a manually allocated project, allocations don't follow task dates. Shifting dates from the project plan's Timeline view moves phases and tasks only. Use Resource Management > Projects > More actions > Shift project dates and select Shift all allocation to move both together. If the plan has already been shifted, move the allocations with a shift allocation request or on the timeline.
Why Do Allocations Appear on a Project When Auto-Allocate Is Off?
Allocations on a manually allocated project can come from:
- earlier use of auto-allocate (allocations generated before it was turned off stay in place)
- the template the project was created from
- approved resource requests
- people with permission to edit allocations, adding them on the timeline
Open the allocation to check. If it shows Auto-allocated for:, it was generated while auto-allocate was on.
If I Switch From Auto-Allocate to Manual, Will Any Hours Change?
No. Total allocated hours and the daily breakdown stay the same after the switch. This applies to the project's Resource management tab, the Resource Management Projects and People tabs, project financials, and portfolio reports.
I Turned On Auto-Allocate and Lost Allocations I Created by Hand. Can I Get Them Back?
No. Turning on auto-allocate deletes every existing allocation on the project, including their custom field values, before generating new ones. Export allocation data before turning it on if a record is needed.
Why Can't I Edit or Split an Allocation?
The project uses auto-allocate, so all allocation fields are read-only and splitting isn't available. Change the task or phase behind the allocation, or turn off auto-allocate to edit allocations directly.
Why Does Someone Have More Than 24 Hours Allocated in a Day?
Auto-allocate doesn't apply the 24-hour-per-day limit. When several tasks assigned to the same person overlap, their hours add up. Fix it by changing task dates, effort, or assignees.
Why Does Someone Have Allocated Hours on a Holiday?
Auto-allocate skips weekends (unless Include weekend is selected) but does not skip holidays. A task that spans a holiday spreads its effort across that day like any other working day.
Why Is the Total Allocated Time Higher Than the Effort I Entered?
Allocations have a minimum of one minute per day. If the effort divided by the number of days comes to less than a minute, each day still receives one minute, which can add up to more than the original effort over a long date range.
Why Didn't an Assignee Get an Allocation?
Allocations are only created for team members, partner users, and your own teams. Customer users and customer teams assigned to a task don't receive allocations. Also check that the task has dates and an effort greater than zero.
Will Changing a Task's Status or Name Change the Schedule?
No. Only effort, dates, assignees, the effort split, weekend inclusion, and the task's default billable setting update allocations.
A Change I Made to a Task Hasn't Appeared in Resource Management Yet. Is Something Wrong?
Probably not. Updates are usually immediate, but when several edits happen on the same project at the same time they are queued and can take a few minutes. Reports can also lag slightly behind the timeline.
Summary
- Each project uses either Auto allocate, where allocations are generated from task or phase effort, dates, and assignees, or Manual, where allocations are created and edited on the Resource Management timeline.
- Turning on auto-allocate deletes every existing allocation on the project. Turning it off keeps all allocations and makes them editable.
- Auto-allocate spreads effort evenly across each task's working days. It skips weekends unless included, but not holidays, and it doesn't apply the 24-hour daily limit.
- On manually allocated projects, effort and task date changes don't move allocations. Shift a project together with its allocations with Shift project dates and Shift all allocation.
- Projects created from a template use the template's allocation mode. Template allocations are copied only into manually allocated projects.